Project Information


  • PROJECT DETAILS : 5 UNITS TYPE-01 (B+G+5) BLOCK (119 HOUSING UNITS) + 14 UNITS TYPE-01 (2F+G+5) BLOCK (361 HOUSING UNITS) + 5 UNITS TYPE-01T (B+G+5) BLOCK (108 HOUSING UNITS + 40 SHOPS) + 4 UNITS TYPE-02 (B+G+5) BLOCK (72 HOUSING UNITS) + 7 UNITS TYPE-04 (B+G+5) BLOCK (252 HOUSING UNITS) + 3 UNITS TYPE-05 (B+G+5) BLOCK (36 HOUSING UNITS) + 6 UNITS TYPE-06 (B+G+5) BLOCK (69 HOUSING UNITS) + 1 UNIT BAKERY
  • INSTITUTION NAME : REPUBLIC OF TURKEY MINISTRY OF ENVIRONMENT, URBANIZATION AND CLIMATE CHANGE HOUSING DEVELOPMENT ADMINISTRATION
  • CONTRACT VALUE : 2,647,000,000.00 TRY + VAT
  • CONSTRUCTION AREA M2 : 158,194.20 M2
  • TENDER DATE : 19/12/2024
  • CONTRACT DATE : 13/01/2025
  • SITE DELIVERY DATE : 17/01/2025
  • COMPLETION DATE : 20/02/2026
  • WORK PROGRESS PERCENTAGE : 10%
×